期刊文献+

天津周大福金融中心深基坑变形综合控制技术 被引量:5

Comprehensive Control Technology for the Deformation of Deep Foundation Excavation in Tianjin CTF Financial Center Project
下载PDF
导出
摘要 以天津周大福金融中心为工程背景,基坑周边环境复杂,毗邻众多重要建筑物,管线密集且部分管线变形已经达到预警值,同时地处天津软土地区的基坑存在着显著的"时空效应",基坑变形引起的负面影响不言而喻,其是整个工程顺利实施的前提,也是工程成败的关键。 In this paper,based on Tianjin CTF Financial Center project,the surrounding environment around the foundation excavation is complex,adjacent to many important buildings,pipeline-intensive and part of the pipeline deformation reaches the early warning value,while located in Tianjin soft soil area there is a significant "space-time effect",the negative impact caused by the deformation of the deep foundation excavation is self-evident,which is the prerequisite for the smooth implementation of the whole project and also the key to the success or failure of the project.
出处 《施工技术》 CAS 北大核心 2017年第23期103-107,115,共6页 Construction Technology
基金 中建八局科技资助(2014-01)
关键词 高层建筑 深基坑 变形 支护 抽条开挖 超前支撑 施工技术 tall buildings deep foundation excavation deformation supports strip excavation advanced support construction
  • 相关文献

参考文献6

二级参考文献14

共引文献172

同被引文献33

引证文献5

二级引证文献29

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部