摘要
水钢1350m3高炉于2017年2月13日停炉,停炉时间长达57天,通过科学、精心的开炉准备和制定合理的开炉方案,顺利实现短时间开炉。仅送风后2天就实现全风口生产。
After 1350 m3 blast furnace of Shuigang had been overhauled for 57 days since it wasblown-out on February 13 in 2017, it was blown-in successfully and rapidly with scientific carefulpreparation and appropriate programs. It was fully blown-in in 2 days since its blowing-in.
作者
郎黔
闫贵州
周成林
Lang Qian;Yan Guizhou;Zhou Chenglin(Technology Center;Iron making Plant, ShougangShuicheng Iron & Steel (Group) Co, Ltd, Liupanshui 553028, Guizhou, China)
出处
《水钢科技》
2017年第4期29-32,共4页
Shuigang Science & Technology
关键词
高炉
开炉
达产
blast furnace
blowing-in
reaching design capacity