摘要 工程活动的空间干涉会延迟活动进度,降低活动质量,甚至引发事故,威胁员工的生命安全。针对这一问题,研究考虑多重空间干涉的工程调度优化问题。对工程中的空间资源和空间冲突进行系统地分类,建立带有多重空间干涉约束的工程调度优化模型并设计一种求解该问题的启发式算法——禁忌模拟退火算法。分别例举一个现实的工程案例和随机生成的算例群进行计算实验,结果表明,算法能快速生成项目调度计划方案,有效避免或减少多重空间干涉并尽可能地缩短工期,为工程管理者提供决策支持。 Space interferences of construction activities can lead to a delay in construction activities, quality defects and safety accidents. To address this issue, this paper investigates the construction scheduling problem with multiple spatial interference. Based on an systematic classification of spatial resources and spatial interferences in construction, an optimization programming model with multiple spatial interference constraints is developed with the tabu simulated annealing (TSA) metaheuristic technique adopted. A real construction case is used for illustration. The experimental results show that the TSA can generate construction activity scheduling plan with less or no multiple spatial interferences and minimal make span. These findings provide useful support for decision making of construction managers in planning construction activities.
作者 陶莎 盛昭瀚
出处 《系统管理学报》 CSSCI CSCD 北大核心 2018年第1期64-71,共8页 Journal of Systems & Management
基金 国家自然科学基金重大项目(71390520 71390521) 国家自然科学基金资助项目(71571098 91646123 71501102 71671088 71471077) 南京大学优秀博士研究生创新能力提升计划资助项目(201601B034)
关键词 工程调度 三维空间资源 空间干涉 活动质量 禁忌模拟退火 construction seheduling three dimensional spatial resource spatial interference quality ofactivity tabu simulated annealing (TSA)
  • 相关文献

参考文献1

二级参考文献12

  • 1万伟,蔡晨.在两资源约束项目环境中的关键链管理[J].中国管理科学,2003,11(z1):4-8. 被引量:9
  • 2蒋国萍,陈英武.基于关键链的项目进度问题研究[C]//章祥荪,王建方,刘宝碇,等.中国运筹学会第七届学术交流会论文集.香港:Global-Link,2004:719-724.
  • 3STEYN H.Project Management Applications of the Theory of the Constraints Beyond Critical Chain Scheduling[J].International Journal of Project Management,2002,20(1):75-80.
  • 4GOLDRATT E M.Critical Chain[M].New York:The North River Press,1997.
  • 5NEWBOLD R C.Project Management in the Fast Lane:Applying the Theory of Constraints[M].NY:St.Lucie Press,1998.
  • 6HERROELEN W S,LEUS R,DEMEULEMEE-STER E L.Critical Chain Project Scheduling:Do Not Oversimplify[J].Project Manage Journal,2002,33(4):48-60.
  • 7LECHLER T G,RONEN B,EDWARDA S.Critical Chain:A New Project Management Paradigm or Old Wine in New Bottles?[J].Engineering Management Journal,2005,17(4):45-59.
  • 8HERROELEN W S,LEUS R.On the Merits and Pitfalls of Critical Chain Scheduling[J].Journal of Operations Management,2001,19(3):559-577.
  • 9SLOWINSKI R.Two Approaches to Problems of Resource Allocation Among Project Activities:A Comparative Study[J].Journal of the Operational Research Society,1980,31(7):711-723.
  • 10张静文,胡信布,王茉琴.关键链项目计划调度方法研究[J].科技管理研究,2008,28(3):280-283. 被引量:18

共引文献10

同被引文献34

引证文献4

二级引证文献26

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部