沿海港口工程施工过程中的赶工措施时有发生,为了完成合同既定的工期目标,必须采取相应赶工措施加快进度,导致在此期间人员、材料、设备的投入增加。为确保对所发生的赶工费用可以准确、合理地进行索赔,必须结合工程所签订的施工合同及所在地相关法律法规条款的要求,有效地对因赶工措施所发生的各项费用进行统计,并与前期投标阶段相关计划投入进行逐一比对,形成有效的量化指标差,从而客观的地对沿海港口工程赶工措施费用进行索赔。文中就如何合理的地对沿海港口工程赶工措施费索赔进行分析,可供类似工程借鉴。
During the construction process of coastal port engineering, we must take corresponding measures to speed up theprocess in order to complete the contract established time limit for a project goal, resulting the input increases in personnel,materials, and equipment during the period. To ensure the crush cost can be accurately and reasonably claimed, must becombined with the construction contract signed by the project and local relevant laws and regulations of requirements, effectivefor expenses incurred by processing measures, and linked to related plans to invest in the premise of tender stage one by one, toform effective quantitative indicators, which objective out measures for coastal port engineering expense claim. In this paper, weanalyzed how to make a reasonable compensation for the crush cost of coastal port project, which can be used for similarprojects.
作者
张磊
石啸
ZHANG Lei;SHI Xiao(No.1 Engineering Co., Ltd. of CCCC First Harbor Engineering Co., Ltd., Tianjin 300456, China)
出处
《中国港湾建设》
2018年第1期71-74,共4页
China Harbour Engineering