运营状态下高架桥的立柱托换施工 被引量:3

Underpinning Construction of Viaduct Columns in Operation Condition
下载PDF
导出
摘要 上海虹桥国际机场需在T1航站楼换乘大厅与轨交10号线车站之间建一条地下通道,但该地下通道恰好正交穿越T1航站楼楼前高架下引桥的正下方,因而需对下引桥4根立柱进行托换,同时还需保证高架桥正常运营。介绍了运营状态下的高架桥立柱托换施工方法、托换结构体系设计和优化、二次托换施工过程中的变形控制技术,并对托换实施效果进行了分析。监测数据显示,托换后的高架桥变形沉降值均在允许范围内,确保了高架桥的结构安全。 Shanghai Hongqiao International Airport needs to build an underground passage between the terminal transfer hall of T1 Terminal and the station of Metro Line 10, which is exactly right below the approach bridge of the viaduct bridge in front of Terminal T1. Therefore, four viaduct columns in lower part of the approach bridge need to be underpinned, and at the same time, the normal operation of viaduct should be ensured. This paper introduces several technologies including underpinning construction method for viaduct column under operational conditions, design and optimization of underpinning structure system, and deformation control technology for secondary underpinning construction process. The implementation effect of underpinning is also analyzed. The monitoring data show that the values of viaduct deformation and settlement are within the allowable range to ensure the structural safety of viaduct.
出处 《建筑施工》 2018年第1期125-128,共4页 Building Construction
关键词 地下连通道 高架桥立柱 二次托换 变形控制 underground channel viaduct column secondary underpinning deformation control
  • 相关文献

参考文献1

二级参考文献14

共引文献32

同被引文献23

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部