摘要 随着10kV设备使用越来越多,涟钢Ⅱ变电站的6kV系统负荷越来越轻,可以考虑退出2台220kV变6kV的主变,减少基本电费,但因涟钢自配发电机较多,6kV系统改变供电模式后存在短路电流超标的问题,故引进深度限流器对事故时超标的短路电流进行限流。 With more and more 10 k V devices put into use, the load of the 10 k V system of Lianyuan Steel's Ⅱ substation becomes lighter and lighter, so it is possible to withdraw two 220 k V to 6 k V transformers to reduce basic electricity consumption. But as the company has more self-owned generators, after changing power supply mode the 6 k V system had the problem of excessive short circuit current, so a depth current limiter was introduced to limit the excessive short circuit current at any failure.
作者 王波 李明和
出处 《冶金动力》 2018年第3期18-22,共5页 Metallurgical Power
关键词 发电机 断路器 短路电流 深度限流器 主变 power generator breaker short circuit current depth current limiter main transformer