关于厦门轨道2号线高林站采用“先隧后站”法修建地铁车站的探讨 被引量:10

Discussion on “tunnel leading platform”to build the Gaolin station of Xiamen metro line 2
下载PDF
导出
摘要 自广州地铁5号线五羊村站、6号线东山口站首次尝试"先隧后站"工法后,北京地铁6号线北运河东站、深圳地铁9号线人民南站等均采用了此类工法。本文根据厦门轨道2号线高林站征收滞后已严重影响"洞通"节点这一事实,对"先隧后站"的工筹、风险、费用估算进行分析,对类似工程有一定的参考意义。 “Tunnel leading platform”have been successfully applied to the wuyangcun station on line 5 and dongshankou station on line 6 of Guangzhou metro,so was beiyunhe east station on line 6 of Beijing metro and renmin south station on line 9 of Shenzhen metro The paper base on the fact that expropriation lag of Xiamen meto line 2 gaolin station has seriously affect the time node,analysis the construction period、risk and cost estimating of “Tunnel leading platform” It has a certain guiding significance for similar projects.
作者 林寅
机构地区 厦门市地铁办
出处 《福建建设科技》 2018年第1期14-16,23,共4页 Fujian Construction Science & Technology
关键词 地铁 先隧后站 工筹工期分析 风险分析 费用估算 metro,tunnel leading platform,analysis of construction period,risk analysis,cost estimating
  • 相关文献

参考文献4

二级参考文献17

共引文献34

同被引文献29

引证文献10

二级引证文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部