石蜡加氢精制装置扩能瓶颈问题分析和改进措施 被引量:2

Bottleneck problem analysis of paraffin hydrogenation unit capacity expansion and improvement measures
下载PDF
导出
摘要 某石化公司炼油厂石蜡加氢精制装置生产能力不足,石蜡总产量仅68.53%被加工成半精炼石蜡,剩余石蜡做为低价的粗石蜡出售,严重影响了石蜡的经济效益。在石蜡加氢装置现有的设备设施基础上,从生产运行状况对装置进行分析,找出了装置高负荷运行条件下的生产瓶颈问题。对装置进行了改造,达到了提高装置负荷的目的,提高了半精炼石蜡的生产能力。 The production capacity of the paraffin hydrorefining unit of the refinery of a petrochemical company is insufficient,only 68.53% of paraffin in total capacity was processed into semi-refined paraffin wax, the remained paraffin was sold as low pricecrude paraffin, and this severely affected the economic benefit of paraffin. Based on the existing equipment and facilities of theparaffin hydrogenation unit, analysis was made to the unit from production operation situation, the production bottleneck problemunder the condition of high load operation of the unit was found out. Renovation was made to the unit, the purpose of improving theload of the unit was realized, and the production capacity of semi-refined paraffin wax was increased.
作者 刘国刚
出处 《炼油与化工》 2018年第1期24-26,共3页 Refining And Chemical Industry
关键词 石蜡 加氢 瓶颈 扩能 paraffin hydrogenation bottleneck capacity expansion
  • 相关文献

同被引文献9

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部