摘要
国外建设标准与国内存在差异,就巴基斯坦路基填筑施工而言,要满足巴基斯坦规范规定的压实度及其他检测项目,需要综合考虑地质情况、气候条件、文化差异等工程建设制约因素。根据国内的施工方法结合巴基斯坦当地施工方法及外界影响因素,总结出适应巴基斯坦路基填筑的施工方法。
There are differences between foreign construction standardsand domestic, in terms of the subgrade filling in Pakistan, the local specifications shall be followed for compaction degree and other test items~ moreover, the geological conditions, climate conditions, cultural differences and other influence factors shall also be taken in to consideration.The construction method of sub-grade filling in Pakistan has been summarized based on the combination of domestic and local practice and conditions.
出处
《工程质量》
2018年第2期57-59,72,共4页
Construction Quality
关键词
巴基斯坦
路基填筑
施工技术
Pakistan: sub-grade filling
construction technology