摘要
既有咽喉区改造需在不影响铁路运营的前提下在封锁点内完成施工,如何能高效、安全、正点、可行地去完成施工任务,关键在于制定切实可行的施工方案,而一个成熟可行的施工方案关键还在于施工步骤,因此本文结合哈尔滨西站哈侧咽喉区改造施工详细论述其施工步骤。
The existing throat area transforming construction should be finished without affecting the operation of the railway during the blockade time, developing a feasible construction scheme is the key point for completing the construction tasks efficiently, safely, punctually and feasibly, and the scheme focuses on the construction process. Therefore, this paper expounded the construction steps combing with the throat area reconstruction of Harbin West Railway Station.
出处
《铁道建筑技术》
2018年第2期34-37,48,共5页
Railway Construction Technology
基金
中铁二十二局集团有限公司科技研发开发计划项目(16-07B)
关键词
大型枢纽站咽喉区改造
18#可动心轨高速道岔
施工方案
施工步骤
不影响铁路运营
reconstruction of throat area of large huh station
18# movable track high speed turnout
construction plan
construction steps
no influence on railway operation