期刊文献+

东海锤入法下入30 in隔水管实践应用 被引量:4

Application of Loading 30 in Drilling Riser with the Hammering Method in the East China Sea
下载PDF
导出
摘要 由于东海某油气田开发需要,从2015年9月到2016年6月先后进行了7口深井、超深井、大位移井钻完井作业,首次应用了锤入法下入30 in隔水管工艺。该气田现场施工前进行了扎实的理论研究,分析了地层承载力大小,确定了隔水管井口载荷及入泥深度,选定了打桩锤等关键设备,在继承并改进前期成熟打桩工艺与理论的基础上,首次成功实践了锤入法下入30 in隔水导管。该项作业的成功,验证了锤入法下入30 in隔水管的可行性,并取得了良好的经济与应用效果,为该项技术推广应用打下了坚实的基础。 For the development of the oil and gas fields in the East China Sea, the hammering method was firstly used to load the drilling riser for the exploitation of 7 deep and ultra-deep wells from September 2015 to June 2016. Before the operation, a deep theoretical study was performed to learn the bearing capacity of the ground, the load of the riser at the top of the well and the driving depth. Critical device such as the pile hammer was chosen, and the loading of 30 in drilling riser was firstly shown with the hammer- ing method based on previous technologies and theories of piling. This study shows the possibility of loading drilling riser with the hammering method, achieving economic and practical application results, laying a solid foundation for the application of this method.
作者 谢领 XIE Ling(CNOOC EnerTech-Shanghai Drilling & Producing Branch, Changning, Shanghai 200335, China)
出处 《海洋石油》 CAS 2018年第1期64-68,共5页 Offshore Oil
关键词 锤入法 30″隔水管 入泥深度 桩锤选取 井口载荷 Hammering method 30 in drilling riser driving depth selection of pile hammer wellhead load
  • 相关文献

参考文献6

二级参考文献29

共引文献36

同被引文献17

引证文献4

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部