Construction of an ultra-deep diaphragm wall:a case study

Construction of an ultra-deep diaphragm wall: a case study
下载PDF
导出
摘要 This paper presents a case study on an ultra-deep diaphragm wall with a depth of 110 m constructed in Ningbo City. The in-situ application shows that using Bauer BC40 cutter machine in conjunction with cutter wheels specified for different strata would be qualified for constructing the 110 m diaphragm wall with high efficiency and precision given that the quality of slurry and poured concrete can be guaranteed. The ground settlement can be effectively controlled by using the overlapping construction method. Sliding failure as a whole characterized by pronounced lateral deformation is likely to occur in the upper muddy clay layer due to its high compressibility and sensitivity. In contrast, local collapse of trench walls tends to happen in the sandy silt strata. Furthermore, careful attention should be paid to sandy silt during the entire construction period as the vertical displacement of the sandy silt continues to develop even atter concrete pouring. This paper presents a case study on an ultra-deep diaphragm wall with a depth of 110 m constructed in Ningbo City. The in-situ application shows that using Bauer BC40 cutter machine in conjunction with cutter wheels specified for different strata would be qualified for constructing the 110 m diaphragm wall with high efficiency and precision given that the quality of slurry and poured concrete can be guaranteed. The ground settlement can be effectively controlled by using the overlapping construction method. Sliding failure as a whole characterized by pronounced lateral deformation is likely to occur in the upper muddy clay layer due to its high compressibility and sensitivity. In contrast, local collapse of trench walls tends to happen in the sandy silt strata. Furthermore, careful attention should be paid to sandy silt during the entire construction period as the vertical displacement of the sandy silt continues to develop even after concrete pouring.
作者 SUN Jie ZHANG Zi-xin HUANG Xin JU Xin 孙杰;zhang zi-xin;黄昕;ju xin(department of geotechnical engineering,tongji university,Shanghai 200092,P.R.China;key laboratory of geotechnical and underground engineering of the ministry of education,tongji university,Shanghai 200092,P.R.China)
出处 《Journal of Chongqing University》 CAS 2018年第1期1-16,共16页 重庆大学学报(英文版)
基金 Funded by the National Basic Research Program of China(973 Program,No.2014CB046905) the National Natural Science Foundation of China(Grant Nos.41172249 and 51509186) the State Key Laboratory for Geomechanics and Deep Underground Engineering(No.SKLGDUEK1303) the funding provided by Zhuhai Da Heng Qin Company Limited(Grant No.SG25-2014-173B1)
关键词 diaphragm wall soft soil quality control SETTLEMENT overlapping method trench cutter BC40 隔膜 案例 构造方法 切割器 淤泥 排水量 土层