摘要
送电、输电线路施工大部分是新建线路工程,但有时会遇到带电运行线路改接线施工,即运行旧线路改造工程。带电线路改接线施工中遇到的问题更多、更复杂,并且需要在短时间完成较重的施工任务。文中通过施工实例,分析总结在停电改接线施工中常会出现的问题,借鉴一些好的施工方法和经验,少走弯路,为以后更多的改线施工提供参考。
Most of the transmission and transmission lines are newly built line projects,but sometimes they will encounter the construction of live lines,which is to transform old lines.The problems encountered in the construction of the electrified line change connection are more and more complicated,and it is necessary to complete the heavier construction task in a short time.Through the construction examples,this paper analyzed and summarized the problems that often occur in the construction of power cut wiring,drawed lessons from some good construction methods and experiences,so as to provide more reference for more reline construction in the future.
作者
孙强
SUN Qiang(Shaanxi Power Transmission & Transformation Company, Xi'an 710014, Chin)
出处
《通信电源技术》
2017年第6期221-222,共2页
Telecom Power Technology