摘要
结合实际工程,对单体特大桥项目结构形式详细研究,以及对施工方案的周密策划,通过技术革新充分挖掘施工过程中的成本降低点,推动项目团队技术力量的建设,提升项目团队科技创新意识,强化项目团队的施工成本意识。其成果可为类似工程提供借鉴。
Combined with the practical projects,the structural style of a large bridge project is studied in detail and the construction scheme is carefully planned.The technical improvement can fully realize the cost saving of construction process to promote the construction of technical force in the project team,to improve the scientific and technological innovation consciousness of project team and to strengthen the construction cost consciousness of project team.The result can be referred for the similar projects.
出处
《城市道桥与防洪》
2018年第4期176-178,共3页
Urban Roads Bridges & Flood Control
关键词
特大桥
旋挖钻成孔施工
气囊移运钢梁技术
large bridge
construction of rotary drill hole
technique of gasbag to remove steel girder