期刊文献+

基于模糊综合评判的汇源大厦改造及湘江大道恢复工程监测 被引量:1

Renovation of Huiyuan building and restoration of Xiangjiang avenue engineering safety monitoring based on fuzzy comprehensive evaluation
下载PDF
导出
摘要 建立基于汇源大厦沉降、倾斜、水平位移、地下水位等监测因素的模糊综合评判模型,评价汇源天桥和汇源大厦裙楼拆除,以及汇源大厦地下室加固和裙楼处湘江大道路面恢复工程施工对毗邻主楼的影响,用于指导对汇源大厦主体工程的沉降(上浮)、倾斜观测、水平位移、地下水位监测和工程的信息化施工,以保障工程的顺利进行。 This paper establishes a fuzzy comprehensive evaluation model based on monitoring factors such as the settlement,tilt,horizontal displacement and groundwater level of Huiyuan Building,which aims to evaluate the impact of the dismantling of the podium building of Huiyuan Bridge and Building,and the reinforcement of the basement and the reconstruction of the Xiangjiang Avenue pavement.It is used to guide the smooth progress of the settlement(floating),tilt observation,horizontal displacement,groundwater level monitoring,and engineering informatization construction of the main project of Huiyuan Building.
作者 贺跃光 鲍建宽 樊明学 肖亮 HE Yueguang;BAO Jiankuan;FAN Mingxue;XIAO Liang(School of Traffic and Transportation Engineering, Changsha University of Science and Technolog, Changsha 410114, China;College of Surverijng and Mapping Engineering, Heilongjiang Institute of Technology, Harbin 150050, China)
出处 《交通科技与经济》 2018年第2期72-76,共5页 Technology & Economy in Areas of Communications
基金 道路灾变防治及交通安全部工程研究中心开放基金资助项目(KFJ150402) 长沙理工大学公路养护技术国家工程实验室开放基金资助项目(kfj150105)
关键词 汇源大厦 拆除工程 模糊综合评判 监测 Huiyuan building demolition project fuzzy comprehensive evaluation monitoring
  • 相关文献

参考文献8

二级参考文献27

共引文献43

同被引文献14

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部