摘要
文中针对石头峡水电站"龙抬头"式泄洪洞进行了模型试验研究,指出原设计体型存在的问题,对泄洪洞"龙抬头"段、出口挑坎体型进行了优化,并进行了试验验证。优化后泄洪洞水流流态较好,壁面未产生过大负压,出口水流归槽良好。
According to the model test study on the spillway tunnel with inlet raised of Shitouxia hydropower station, the existed problems in the original design shape are pointed out. the shapes of flip bucket of spillway tunnel with inlet raised and outlet are optimized and verified. The water flow pattern of the optimized spillway is better, no excessive negative pressure on the wall and the outlet flow coming into main channel is good.inlet tower of spillway tunnel.
出处
《东北水利水电》
2018年第5期44-46,共3页
Water Resources & Hydropower of Northeast China
关键词
龙抬头泄洪洞
模型试验
挑坎
体型优化
spillway tunnel with inlet raised
model test
flip bucket
shape optimization