介绍制氢装置水煤浆气化技术改造后运行情况,针对多次出现的气化炉合成气出口堵渣问题,进行原因分析,提出改进优化措施,效果明显。
The operation of water coal slurry gasificationafter technical transformation in hydrogen preparation plant was described. For blockage often occurred at syngas outlet in the gasifier, the improvement measures after studying the reasons were presented and showed good results.
作者
曹志普
张光辉
庞刚
Cao Zhipu;Zhang Guanghui;Pang Gang(SINOPEC Jiujiang Branch, Jiujiang 33200)
出处
《大氮肥》
CAS
2018年第2期73-74,共2页
Large Scale Nitrogenous Fertilizer Industry
关键词
气化炉
合成气管线
堵渣
优化
gasifier
syngas line
slag blockage