阳江LNG调峰储气库与外输管线首站压力匹配研究

Yangjiang LNG Peaking Storage Gas Storage and Outer Pipeline First Station Pressure Matching
下载PDF
导出
摘要 针对阳江LNG调峰储气库项目外输管线工程设计过程中输气干线首站和调峰储气库设计压力不匹配问题,从设计源头探究设计压力不匹配原因,分析压力不匹配带来的潜在问题,提出了相应解决措施,并结合实际提出本质安全解决方案,即将首站设计压力提高至与储气库外输系统设计压力一致。 According to the design pressure mismatch problem between the first station of the main gas transmission line and the peaking gas storage in the design process of the Yangjiang LNG peaking and gas storage project, the reason for the design pressure mismatch was explored from the source of the design and the pressure mismatch was analyzed.From the potential problems, the corresponding solutions were proposed, and the intrinsic safety solutions were put forward in combination with the actual situation, that is, the design pressure of the first station was increased to the design pressure of the gas storage system.
作者 董斌 王晓虎 孙英蕃 Dong Bin;Wang Xiao-hu;Sun Ying-bo
出处 《化工设计通讯》 CAS 2018年第4期14-14,共1页 Chemical Engineering Design Communications
关键词 液化天然气 输气干线 首站 设计压力 liquefied natural gas gas transmission line first station design pressure
  • 相关文献

参考文献1

二级参考文献9

共引文献25

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部