摘要 坝基处理是修建大坝的关键,处理不当会留下工程缺陷,甚至隐患。针对沙坡头水利枢纽泄洪闸及南干电站坝段帷幕缺陷问题进行了四次帷幕补强处理,并对其经验、成果进行分析,探讨在泥岩、砂岩、软岩等复杂地质条件下,如何合理制定帷幕灌浆施工方案,达到帷幕缺陷处理的预期效果,解决大坝帷幕灌浆隐患。研究结论可为其他工程提供借鉴。 Dam foundation treatment is the key to build a dam,and engineering defects and even hidden danger will be left due to improper treatment. Curtain reinforcement treatment is carried out for four times mainly aiming at curtain defect problems in Shapotou key water control project sluice and Nangan power station dam section. Experience and results are analyzed for discussing how to rationally formulate curtain grouting construction plan under mudstone,sandstone,soft rock and other complicated geological conditions,thereby reaching curtain defect treatment anticipated effect,solving dam curtain grouting hidden danger. The research conclusions can provide reference for other projects.
作者 白玉龙 BAI Yulong(Ningxia Shapotou Key Water Control Project Co., Ltd., Yinchuan 750001, China)
出处 《水利建设与管理》 2018年第4期67-71,共5页 Water Conservancy Construction and Management
关键词 水利枢纽 软基岩 帷幕缺陷 补强灌浆 处理经验 key water control project soft base rock curtain defect strengthening grouting treatment experience
  • 相关文献

同被引文献9

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部