摘要
以200t/d垃圾热解发电项目为例,分析了1~20年内的经济指标,计算了动态投资回收期及投资收益率,为以后类似项目的启动提供了一定的依据。
Taking the 200t/d life garbage pyrolysis power generation project as an example, economic indicators were analysed in 20 years. The dynamic investment recovery period and return on investment was calculated to provide some basis for the launch of similar projects in the future.
作者
张宏伟
Zhang Hongwei(Beijing Iron & Steel Metallurgical Energy Saving & Emission Reduction Engineering Technology Research Center,Beijing 100029;Beijing Metallurgical Equipment Research Design Institute Co . Ltd. Beijing 100029)
出处
《冶金设备》
2018年第2期59-62,共4页
Metallurgical Equipment
关键词
生活垃圾
发电
热解
Life garbage Power generation Pyrolysis