摘要
以实际工程为例,重点对喀斯特地区桩基施工技术进行分析和探讨,对难点工程问题进行合理处理,降低了工程造价,保证了施工工期,可供类似工程借鉴。
Taking the actual project as an example, focusing on the construction technology of pile foundation in Karst area are analyzed and discussed. The difficulty of the engineering problems of reasonable processing, reduce engineering cost and ensure the construction period, in order to reference for similar projects.
作者
郭剑锐
GUO Jian-rui(CR17BGConstruction EngineeringCo.L~.,Taiyuan 030031,China)
出处
《工程建设与设计》
2018年第9期229-231,共3页
Construction & Design for Engineering
关键词
喀斯特地区
桩基施工技术
地质勘探
karst area
pile foundation construction technology
geological exploration