摘要
介绍某铁路临时施工用电供电受限,结合周边相关110 k V和35 k V变电站、35 k V线路的供电能力、供电可靠性等进行供电方案对比分析,得出综合最优解决方案。此方案既解决了供电受限问题,又优化了规划项目,同时也实现电网资源共享、电网分层分区供电。
The temporary construction of Mojiang section of Yu Mo Railway Limited power supply, combined with the related 110 kV and 35 kV substation、35 kV line power supply capacity、power supply reliability of power supply scheme comparison, get the optimal solution. This scheme not only solves the problem of power supply limitation, but also optimizes the planning project. At the same time, it also realizes the sharing of power grid resources and the power supply of layered and partitioned power grid. In order to solve the similar problem of power supply limitation.
作者
杜秀平
DU Xiuping(Yuxi Power Supply Bureau of Yunnan Power Grid Co., Ltd.,Yuxi,Yunnan 653100,China)
出处
《云南电力技术》
2018年第2期7-8,共2页
Yunnan Electric Power
关键词
电网规划
供电受限
资源共享
铁路施工临时用电
设备利用率
Power grid planning
power supply is limited
resource sharing
railway construction temporary electricity
equipment utilization