摘要
利用PSD-BPA软件对特高压投产前后河北省南部电网500 kV电压进行计算分析,计算结果表明:特高压投产后河北省南部电网500 kV电压水平普遍提高,同时造成部分500 kV站点低压侧电压过高,使得电容器难以投入,限制了电网电压调整能力,分析结果可为以后500 kV变压器额定电压的选取提供参考。
PSD-BPA software is used to calculate and analyze the 500 kV voltage of Hebei southern power grid before and after UHV operation. The results show that the voltage level of 500 kV in Hebei southern power grid is generally increased after the UHV is put into operation,and the voltage on the low voltage side of some 500 kV stations is too high,which makes the capacitor difficult to be put into operation,which limits the voltage regulation ability of the grid. The analysis results can provide reference for the selection of the rated voltage of 500 kV transformer.
作者
陈丽
师立涛
Chen Li;Shi Litao(Hebei Electric Power Design & Research Institute, Shijiazhuang 050031, China)
出处
《河北电力技术》
2018年第1期5-7,共3页
Hebei Electric Power
关键词
特高压
500
KV电网
电压水平
无功协调控制
ultra high voltage(UHV)
500 kV network
voltage level
reactive voltage control