摘要
乌兰察布游泳馆网球馆钢结构工程主要由桁架结构的网球馆、热身馆和张弦梁结构的游泳馆组成。通过其钢结构安装工程,系统介绍了其施工过程中的新技术应用,同时也阐述了各个单体结构的施工方案,较详细地说明了游泳馆张弦梁张拉的关键技术。
Ulanqab natatorium tennis court is composed of tennis court and warm-up pool pavilion which structure is truss,and natatorium which structure is beam string. Through the installation project of the steel structure,the application of new technology in the construction was systematically introduced. Moreover,the paper fully illustrated the construction scheme of each single structure,especially the key techniques of the extension of beam string structure.
作者
李银标
李奇奇
童早娟
景辉
LI Yinbiao;LI Qiqi;TONG Zaojuan;JING Hui(Zhejiang Jinggong Steel Building Group Co. Ltd, Shaoxing 312030, China;China Aviation Planning and Construction Development Co. Lid, Beijing 100120, China)
出处
《钢结构》
2018年第4期97-100,12,共5页
Steel Construction
关键词
桁架
钢拉杆
张弦梁
支撑架
truss structure
steel tie bar
beam string structure
supporting frames