期刊文献+

大跨度T构曲梁墩顶转体施工控制 被引量:2

On the Construction Control of the Pier-Top Rotation of the Large-Span T-Shaped Curved Beam
下载PDF
导出
摘要 以商合杭上跨徐兰高铁T构梁为研究对象,针对大跨度T构曲梁墩顶转体施工控制技术展开研究。在MIDAS中对桥梁施工全过程进行了仿真分析,确定了不平衡力矩、顶升力等关键参数,据此对该桥进行了线形控制、应力控制及转体不平衡弯矩测试。结果表明:桥梁线形平顺,与设计线形吻合度良好;悬臂施工阶段及转体阶段桥梁处于全截面受压状态。为其他类似桥梁的施工控制提供参考。 With the T-shaped girder of the Shang-He-Hang Railway over-crossing the Xu-Lan High Speed Railway as the object of our research,the construction control techniques for the pier-top rotation of large-span T-shaped curved beam are studied in the paper. With the help of the MIDAS,the whole process of the bridge construction is simulated and analyzed,with the key parameters of the unbalancing moment, the lifting power and the like determined, in the light of which the alignment and stress of the bridge are controlled, and the unbalancing bending moment of the rotation is tested. The tested results show that the a- lignment of the bridge is flat, smooth and in full agreement with the designed alignment. During the cantilever construction stage and the rotation stage, the full cross-section of the bridge is in the state of being pressurized. The paper may serve as a useful reference for the construction control of other similar bridges.
作者 贾培亮 JIA Peiliang(The 17th Bureau Group of China Railway,Taiyuan 030051,China)
机构地区 中铁十七局集团
出处 《国防交通工程与技术》 2018年第3期78-81,50,共5页 Traffic Engineering and Technology for National Defence
关键词 大跨度T构桥 曲梁 墩顶转体 施工控制 large-span T-shaped bridge curved beam pier-top rotation construction control
  • 相关文献

参考文献4

二级参考文献15

共引文献42

同被引文献15

引证文献2

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部