摘要
介绍了广西左江治旱驮英水库及灌区工程的基本情况和渠道总体线路水工布置设计思路,针对丘陵地区地形地貌特点,通过对宁明干渠高低两线方案的地形条件、补水效益、施工条件、征地、投资等方面进行比选,推荐高线方案进行驮英灌区宁明干渠线路布置。
An introduction was made on the basic information of Tuoying Reservoir and Irrigation Zone Project, andon the general layout of channels. In view of the landform characteristics of hilly area, two Ningming trunk channellayout alternatives were compared in respects of topographical conditions, water supplementing benefits, construc-tion conditions, land requisition and cost, before the upper route scheme was selected.
作者
孟凡雷
MENG Fan-lei(Guangxi Water and Power Design Institute, Nanning 530023, Chin)
出处
《广西水利水电》
2018年第2期48-50,共3页
Guangxi Water Resources & Hydropower Engineering
关键词
灌区
线路布置
方案比选
驮英水库
hTigation zone
layout
comparison and selection of scheme
Tuoying Reservoir