浅述抽水蓄能电站土石方平衡设计及过程调配管理 被引量:1

Analysis of the design of the Earthwork Balance and Allocation management in Pumped-storage Power Station
下载PDF
导出
摘要 本文从抽水蓄能电站土石方平衡一般设计思路出发,梳理了料源平衡时序冲突、开挖料利用系数取值不合理、过程监督缺失等近年来在设计计算以及动态管理中出现的一些常见问题,分析了各项问题发生的潜在原因,指出了建设过程中参建各方的职责,并给出了关于土石方平衡设计与过程调配管理的建议。 This paper combs out some of the problems which exists in the process of construction management based on the design concept of the earthwork balance,such as scheduling conflict,calculation error,lack of process supervision,analyzed the potential causes of these problems,and points out the responsibility of each unit At last,suggestions on the design of the earthwork balance and Allocation management are presented.
作者 温家华 潘福营 WEN Jiahua;PAN Fuying(Technology Center, State Grid Xinyuan Co. Ltd, Beijing 100161, China;State Grid Xinyuan Co. Ltd, Beijing 100761, China)
出处 《水电与抽水蓄能》 2018年第2期117-120,共4页 Hydropower and Pumped Storage
关键词 抽水蓄能电站 土石方平衡 调配管理 pumped-storage power station earthwork balanceallocation management
  • 相关文献

参考文献6

二级参考文献24

  • 1王晓梅,梁轶.大系统理论在面板堆石坝工程土石方平衡规划中的应用[J].水利水电快报,2001,22(17):14-17. 被引量:14
  • 2郑家祥,殷奎生.高土石坝施工过程计算机模拟[J].水电站设计,1993,9(2):70-75. 被引量:7
  • 3张松.南水北调中线工程土石方调配优化(学位论文)[M].武汉:武汉水利电力大学,1999..
  • 4能源部、水利部颁发.施工组织设计规范[M].北京:水利电力出版社,1990..
  • 5KruglinskiJ WingoS.Visual C++ 6.0 技术内幕[M].北京:北京希望电子出版社,2001..
  • 6袁光裕编.水利工程施工(第三版)[M].北京:中国水利水电出版社,2001..
  • 7水利电力部水利水电建设总局.水利水电工程施工组织设计手册(第二卷)[M].北京:水利电力出版社,1990..
  • 8运筹学教材编写组编.运筹学(修订版)[M].北京:清华大学出版社,1998..
  • 9郭科.最优化方法及其应用[M].北京:高等教育出版社,2007.
  • 10袁光裕,水利工程施工,1996年

共引文献61

同被引文献6

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部