摘要
介绍了泗洲选矿厂HP500圆锥破碎机更新安装时,设备基础材料选用CGM灌浆料,圆锥破碎机底板采用无垫铁安装法安装。圆锥底板采用地脚螺栓与底板一体化安装法,简化了安装工序,提高了安装效率和安装精度,缩短了施工周期,圆锥基础受力更均匀,稳定性更好。
When the HP500 cone crusher installed in Sizhou concentrator, the CGM grouting material is used as the basic materialof the equipment, and the bottom plate of crusher is installed with the iron free installation method. The cone crusher adopts theintegral installation method of the anchor bolt and the bottom plate, so the installation procedure is simplified. The construction cycle isshortened, and at the same time the installation efficiency and installation accuracy are improved. The bottom plate of crusher bears moreuniform force and the stability of cone crusher operation is improved.
作者
王刚
葛根法
蒋建明
姜光荣
谭红林
WANG Gang;GE Gen-fa;JIANG Jian-ming;JIANG Guang-rong;TAN Hong-lin(Dexing Copper Mine, Jiangxi Copper Corporation, Dexing 334224, Jiangxi, Chin)
出处
《铜业工程》
CAS
2018年第2期81-83,共3页
Copper Engineering
关键词
HP500圆锥破碎机
无垫铁安装法
二次灌浆
简化工序
缩短工期
运行稳定
HP500 cone crusher
erection without pad iron
secondary grouting
simplifing working procedure
shortenconstructionperiod
operation stability