摘要
根据合景天峻广场二期项目桩基工程,对高压旋喷硫铝酸盐水泥浆液处理桩缺陷的施工全过程进行了阐述。通过对高压清水旋喷切割、清洗桩底沉渣及高压喷射低碱度硫铝酸盐水泥浆液等技术的研究,达到处理桩底沉渣及加固补强的目的。
According to the pile foundation project of the phase II of Hejing Tianjun Square,the whole process of the construction of high pressure jet grouting with sulfur-aluminate cement slurry to deal with pile defect is expounded. Through the study of the process of high pressure clean water jet cutting,cleaning the bottom sediment and high-pressure jet grouting of low alkalinity sulfur-aluminate cement slurry,the purpose of the disposal of bottom sediment and reinforcing of pile bottom is achieved.
作者
罗涛
肖玉明
唐光暹
LUO Tao1, XIAO Yuming1, TANG Guangxian2(1. Guangxi Construction Engineering Group Co. ,Ltd. , Nanning, Guangxi 530201,China; 2. Guangxi Construction Engineering Group Infrastructure Construction Co. ,Ltd. , Nanning, Guangxi 530201, Chin)
出处
《施工技术》
CAS
2018年第9期22-24,共3页
Construction Technology
关键词
桩基础
高压旋喷
硫铝酸盐水泥
桩缺陷
施工技术
piles
high pressure jet grouting
sulfur-aluminate cement
pile defects
construction