采煤工作面底板突水机理研究及注浆堵水技术应用

Research on Mechanism of Water Bursting in Coal Face and Application of Grouting and Water Shutoff Technology
下载PDF
导出
摘要 金鼎煤业二1煤层开挖后引起应力重新分布使底板岩体应力环境进一步恶化, 加剧了底板原有裂隙和结构面的扩展、错动、贯通, 甚至产生新裂隙.当这些原生结构面和新裂隙与下伏高压含水层沟通形成导水通道时便导致矿井突水, 利用先进注浆堵水技术仅用205天便成功堵水, 堵水率100%. The stress redistribution caused by the excavation of No.21 coal seam in Jinding Coal Mine further aggravates the stress environment of the floor rock mass, exacerbating the original cracks and structural planes in the floor, expanding, dislocating, penetrating and even creating new fractures. When these primary structures when the surface and new fractures communicate with the underlying high-pressure aquifer to form the aqueduct, it will lead to water inrush in the mine. By using advanced grouting technology, water can be blocked only in 205 days and the water plugging rate is 100%.
作者 刘松 LIU Song(Zhengzhou Xianglong Geological Engineering Co., Ltd.,Xinmi Henan 452371)
出处 《河南科技》 2018年第7期93-94,共2页 Henan Science and Technology
关键词 突水机理 卸荷力学 突水模式 截流堵源 water inrush mechanism;unloading mechanics;water inrush mode;interception plugging source
  • 相关文献

参考文献1

二级参考文献10

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部