摘要
以磁窑沟煤矿10201工作面设备回撤及新工作面安装为例,详细介绍了搬家倒面前期开展的必要性准备工作及通道支护工程,以及通过采用合理的回撤工艺、快速的运输方式,最终利用9天时间安全顺利的完成了综采搬家倒面,对于推进安全高效矿井建设具有重大意义。
Taking equipment evacuation of 10201 face, Ciyaogou Colliery and new face installation for instance, the paper introduced necessary preparations for the early stage and channel support engineering of moving converted section. By using reasonable evacuation technology and rapid transportation, moving converted section has been completed safely and smoothly in 9 days, which has great significance for promoting safe and efficient mine construction.
作者
刘显验
李雪莲
Liu Xianyan;Li Xuelian(Shanxi Hequ Jinshen Ciyaogou Coal Industry Co.,Ltd.,Xinzhou,Shanxi 036500;Shanxi Jinshen Energy Group Co.,Ltd.,Xinzhou,Shanxi 036500)
出处
《江西煤炭科技》
2018年第2期124-126,共3页
Jiangxi Coal Science & Technology
关键词
综采工作面
搬家倒面
快速
fully mechanized coal face
moving converted section
rapid