摘要
针对梅县发电厂春雨季节或台风雨季节,因来煤湿导致输煤系统及锅炉给煤系统堵塞,进行湿煤与灰掺混,并进行等级警报,取得了防堵塞的良好效果,保障了燃料的正常供给,确保了机组的正常运行。
Aiming at spring rain season or Typhoon rain season in power plant in Meixian, the coal conveying system and boiler feed system are blocked due to coal dampness. Measures such as wet coal mixed with ash and level alarms have been taken,which has achieved good anti-clogging effect, ensured the normal supply of fuel and the normal operation of the unit.
作者
刘宇梅
Liu Yumei(Guangdong Yuediandabu Power Co., Ltd., Meizhou, Guangdong 514733)
出处
《江西煤炭科技》
2018年第2期127-128,131,共3页
Jiangxi Coal Science & Technology
关键词
煤湿
给煤系统
警报
掺灰
防堵塞
coal dampness
coal feeding system
alarm
mixed with ash
anti-clogging