摘要
采用计算机仿真技术对观音岩水电站厂房施工过程进行模拟,研究在不同机械配置情况下施工方案的比较优选。通过模拟不同浇筑机械配置方案的水电站厂房施工浇筑过程,分析机械配置对厂房施工进度、月浇筑强度、机械利用强度等技术指标的影响,得出优化后的施工方案使施工过程的浇筑能力接近饱和状态,说明采用计算机仿真技术优化水电站厂房施工方案是可行的。
The computer simulation technology was used to simulate the construction process of Guanyinyan Hydropower Station, and the construction scheme under different mechanical configurations was optimized. Through simulating construction process of the hydropower plant with different pouring machine configuration schemes, the article analyzes the influence of the mechanism arrangement on technical indicators of construction progress, monthly pouring strength and mechanical utilization strength of the plant. The optimized construction plan was adopted to make the pouring capacity of the construction process close to saturation. The state indicates that it is feasible to use computer simulation technology to optimize the construction scheme of the hydropower station.
作者
郭大平
胡良才
纪俊双
Guo Daping,Hu Liangcai,Ji Junshuang(China Nuclear Fourth Research Design Engineering Co., Ltd. Shijiangzhuang 050021, Hebei;Hebei Provincial Water Resources and Hydropower 2nd Survey and Design Institute Shijiangzhuang 050021, Hebe)
出处
《陕西水利》
2018年第3期155-157,160,共4页
Shaanxi Water Resources
关键词
水电站厂房
混凝土浇筑
施工仿真
Hydropower plant
concrete placement and construction simulation