综采液压支架回收顺序及工艺研究

Study on Recovery Sequence and Process of Fully Mechanized Hydraulic Support
下载PDF
导出
摘要 香源煤业公司在1206综采工作面回撤过程中,对综采液压支架的回撤顺序及施工工艺进行了相关研究,回撤结果表明,与传统回撤工艺相比,回收时间节约60~70%,提高了支架回收的安全性。 During the retracting process of 1206 fully mechanized coal mining face, Xiangyuan Coal Company studied the retracting order and construction technology of fully mechanized hydraulic support. The retracting results showed that the recovery time saves 60 to 70% compared with the traditional retracting process, which improved the safety of the support recovery.
作者 白晓生 Bai Xiao-sheng(Shanxi Fenxi Xiangyuan Coal Industry Co., LTD., Shanxi Jiaocheng 03050)
出处 《山东煤炭科技》 2018年第5期62-64,共3页 Shandong Coal Science and Technology
关键词 综采 支架 回收 工艺 fully mechanized working support recovery process