挖金湾矿注浆锚索加固技术的实践应用

Practical Application of Grouting Anchor Cable Reinforcement Technique in Wajinwan Mine
下载PDF
导出
摘要 以大同煤矿集团挖金湾矿8103综放面为研究对象,采用注浆锚索加固技术,对巷道二次支护。结果表明注浆锚索加固后的巷道两帮移近量比非注浆锚索段减少333mm,顶底板移近量减少483mm,保证了工作面正常回采需要。 Taking the 8103 fully mechanized top coal caving face of Wajinwan Coal Mine in Datong Coal Mine Group as the research object, the grouting and anchor cable reinforcement technology is adopted to support the roadway two times. The results show that the two displacement of the roadway after the grouting anchor cable is 333 mm less than that of the non-grouting anchor cable, and the displacement of the top floor is 483 mm, which ensures the coal mining needs of the working face.
作者 苏国超 Su Guo-chao(Hongtai Mine Engineering Construction Co., LTD., Datong Mining Group, Shanxi Datong 03700)
出处 《山东煤炭科技》 2018年第5期74-76,共3页 Shandong Coal Science and Technology
关键词 动压 巷道 注浆 锚索 dynamic pressure roadway grouting anchor cable
  • 相关文献

参考文献5

二级参考文献12

共引文献31

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部