摘要 对某高速公路1-55m钢筋混凝土拱桥因不能满足立交区匝道、变速车道布设要求,需拆除重建。对机械拆除和爆破拆除两种方案进行综合对比,结果表明,爆破拆除在造价、保通方面均具有优势,推荐使用,方案比选步骤可供同行参考。 Due to the reason that 1 -55m reinforced concrete arch bridge of an expressway fails to meet therequirement of layout for interchange or speed change lane, it is necessary to perform the demolition andreconstruction. The comprehensive comparison for two kinds of schemes like mechanical demolition and blastingdemolition is made. The results show that, the blasting demolition is recommended to use with merits in aspects likeconstruction cost, traffic guaranteeing, so as to provide reference for the scheme comparison step.
作者 汪海涛 WANG Hai-tao(Liaoning Provincial Communication Planning and Design Institute Co. .Ltd. .Shenyang 110166.China)
出处 《北方交通》 2018年第5期50-52,55,共4页 Northern Communications
关键词 钢筋混凝土拱桥 机械拆除 爆破拆除 微差爆破 Reinforced concrete arch bridge Mechanical demolition Blasting demolition Millisecond blasting
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部