某大型综合建筑裙楼及地下室基础设计优化分析 被引量:1

Optimization Analysis about Design of the Podium Building and Basement in a Large Complex Building
下载PDF
导出
摘要 在某大型综合建筑的裙楼及地下室基础设计时,设计单位原采用灌注桩基础设计,根据拟建场地的地质水文条件以及上部结构荷载情况,估算确定了几种可选择的基础形式,并对这几种基础形式在工期、质量、造价、施工可行性等方面进行综合比较,建议采用静压预应力管桩,实施后取得良好的技术经济效果。 During the design of the podium building and basement in a large complex building,the design unit use cast-in-place pile foundation at the beginning. Based on the proposed site geological and hydrological conditions and the upper structure load conditions,the article estimates the basis of several alternative forms,and on this foundation types in the construction period,quality,cost,construction feasibility,etc. are compared. Finally the statically pressed prestressed pipe pile are recommended,and it obtained good technical and economic effect after implementing.
作者 程志辉 刘少浪 Cheng Zhihui;Liu Shaolang(Architectural Design & Research Institute of SCUT Guangzhou 510641, China)
出处 《广东土木与建筑》 2018年第5期65-67,共3页 Guangdong Architecture Civil Engineering
关键词 内力估算 基础承载力 旋挖灌注桩 预应力管桩 抗拔锚杆 the internal force estimation bearing capacity of foundation revolving digging cast-in-place bored pile prestressed pipe pile uplift anchor uplift anchor
  • 相关文献

参考文献2

二级参考文献3

共引文献10

同被引文献3

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部