上软下硬富水地层盾构法施工技术研究 被引量:17

Construction Technology Study on Shield Method Applied in Upper-soft and Lower-hard Water-rich Stratum
下载PDF
导出
摘要 以广州地铁4号线大涌站~塘坑站盾构区间为例,分析盾构法施工在上软下硬地层中存在的掘进缓慢、刀具磨损严重、喷涌、结泥饼等难点和风险,详细介绍盾构法在上软下硬地层中施工的参数控制、渣土改良等关键技术,并为类似工程提供参考。 Taking the shield interval construction of Dayong Station - Tangkeng Station in Guangzhou Metro Line 4 as an example, this paper analyzed the difficulties and risks existed in upper-soft and lower-hard stratum with shield method, such as slow driving, serious tool abrasion, spewing, mud ling. Then, the paper discussed the key technologies of parameters control and residue improvement about shield method used in the construction of upper-soft and lower-hard stratum. It could be served as a reference for similar projects.
作者 李达 Li Da(China Railway 19thBureau Group Rail Transit Engineering Co. Ltd. , Beijing 101300, China)
出处 《铁道建筑技术》 2018年第5期68-69,91,共3页 Railway Construction Technology
基金 中铁十九局集团有限公司科技研究开发计划项目(15-14B)
关键词 上软下硬地层 盾构法 参数控制 渣土改良 upper-soft and lower-hard stratum shield method parameter control residue improvement
  • 相关文献

参考文献11

二级参考文献81

共引文献307

同被引文献158

引证文献17

二级引证文献84

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部