降料面喷补造衬在长钢9号高炉的实践应用

Practical Application of Gunning Lining in Lowering Charge Level in No.9 Blast Furnace of Changzhi Steel
下载PDF
导出
摘要 通过对长钢9号高炉采用打水空料线停炉法修补无冷区以及复风过程进行总结,空料线耗时5 h,实现安全、快速、经济、准确的目标。复风通过对炉温、碱度、上下部调剂等实现快速稳定恢复,喷涂造衬取得了停炉时间短、炉况恢复快,高炉指标明显改善。 Through the summary of the cold zone recovery and reblowing process by furnace shutdown in descending stockline of No. 9 blast furnace of Changzhi Steel, the descending stockline takes 5 h, so as to achieve a safe, rapid,economical and accurate target. The recovery of temperature, alkalinity and the upper and lower parts of the furnace is fast and stable. The gunning lining has obtained the short time of furnace shutdown and fast recovery of the furnace.And the index of the blast furnace is obviously improved.
作者 马永芳 王保国 Ma Yongfang;Wang Baoguo(Shougang Changzhi Steel & Iron Co., Ltd., Changzhi Shanxi 046031)
出处 《山西冶金》 CAS 2018年第2期75-77,80,共4页 Shanxi Metallurgy
关键词 降料面 停炉 喷补造衬 复风 lowering charge level furnace shutdown gunning lining reblowing
  • 相关文献

参考文献2

共引文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部