平朔东露天矿特大型选煤厂建设施工管理

Rapid and efficient construction management for extra-large coal preparation plant of Pingshuo East Open-pit Mine
下载PDF
导出
摘要 为了快速高效地完成平朔东露天煤矿特大型选煤厂项目建设,从安全、速度、环保和成本等多方面因素,以新技术研究和应用为支撑,研究了特大直径钢筋混凝土预应力原煤仓施工技术、产品煤槽仓施工技术、大型工业厂房设备安装施工技术。现场施工结果表明,平朔东露天矿特大型选煤厂优质、安全、快速地完成施工,实现了预定目标,获得了良好的社会和经济效益。 In order to quickly and efficiently complete the construction of the Pingshuo East Open-pit Coal Mine extra-large Coal Preparation Plant,the project department comprehensively considered various factors such as safety,speed,environmental protection and cost, and actively carried out technical research to support the development of new technologies. Construction of reinforced concrete pre-stressed coal bunker warehouse and research, construction and research of product coal trough warehouse, installation and construction of large-scale industrial plant equipment and research and other technical issues, and ultimately completed the construction with high quality, safety, and rapid,achieved the desired goal and achieved good results. Favorable social and economic benefits were achieved.
作者 吴春杰 李志中 WU Chun-jie;LI Zhi-zhong(China Coal 72 Engineering Co., Ltd., Suzhou 234000, Chin)
出处 《煤炭工程》 北大核心 2018年第6期164-167,共4页 Coal Engineering
关键词 东露天矿 特大型选煤厂 大直径原煤仓 Pingshuo East Open-pit Mine extra-large coal preparation plant large diameter raw coal silo
  • 相关文献

参考文献2

二级参考文献13

  • 1马杰.液压滑升模板施工偏差与调整.滑模工程,1991,(2):34-36.
  • 2GB50204-2002,钢筋混凝土结构工程施工质量验收规范[S].
  • 3GB50010--2010混凝土结构设计规范[S].
  • 4GB50077-2003.钢筋混凝土筒仓设计规范[S].[S].,..
  • 5GB 50215-2005,煤炭工业矿井设计规范[S].
  • 6JGJ65-89,液压滑动模板施工安全技术规程[S].
  • 7GB 50113-2005滑动模板工程技术规范[S].
  • 8GB50191-2012,构筑物抗震设计规范[S].
  • 9GB50017-2003,钢结构设计规范规范[S].
  • 10建筑施工手册(第四版)编写组.建筑施工手册(第四版)[M].北京:中国建筑工业出版社,2006.