基于关键路径法的某核电站反应堆厂房主体工期优化分析 被引量:2

Duration Optimization of the Main Part of Reactor Building of One Nuclear Power Plant Based on Critical Path Method
下载PDF
导出
摘要 核电站反应堆厂房主体施工是整个核岛土建工程的核心,也是进度控制重点。反应堆厂房主体施工的工期由关键路径上的工作持续时间决定,任何一个关键工作的延误都将直接影响到工程进度。通过对反应堆厂房主体施工关键路径的分析,明确了主体施工各条施工路径间的内在逻辑关系,为工期优化分析提供了着力点。 The construction of main body of reactor building is the core of the civil engineering of the whole nuclear island, is also the focus of progress control. The duration of the construction of the main body of the reactor building is determined by the duration of the work on the critical path, any delay of the critical work will directly affect the progress of the project. Analysis on critical path of main body construction of reactor building, it shows the inner relationship between the construction paths of the main construction, and it also provides the basis for the analysis of duration optimization.
作者 周伟 ZHOU Wei(China Nuclear Industry Huaxing Construction Company Limited, Nanjing 210019,China)
出处 《工程建设与设计》 2018年第12期238-240,共3页 Construction & Design for Engineering
关键词 核电站 反应堆厂房 关键路径 工期优化 nuclear powor plant reactor building critical path duration optimization
  • 相关文献

参考文献3

二级参考文献6

  • 1王辉诚,陈立胜,吕光晔.核电站高性能大体积混凝土配制与施工技术[J].核动力工程,2011,32(S2):47-50. 被引量:6
  • 2刘镐.大型压水堆核电站双层安全壳施工技术探讨.233网校论文中心.2010.
  • 3史春元,王建国,金成,等.预制应力法控制核电站钢衬里简体壁板焊接变形的研究[J].2012第八届中国北方焊接学术会议论文集.2013.
  • 4慧聪工程机械网TlT.福清核电采用了欧维姆锚固体系和张拉设备[J].2013.08.
  • 5廖春生.台山核电站1号核岛安全壳预应力施工完成[s].中核华兴.2014.01.
  • 6王开华.范群喜,祖斌,等.我国核电站综合建造技术与工程管理研究成果[s].中国核工业建设集团公司.2005.12.

共引文献18

同被引文献8

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部