摘要
在国家大力推行装配式建筑的背景下,以上海市某项目为例,对比装配式结构和现浇式结构的成本,分析装配式构件成本居高不下的原因,找出影响成本的主要因素,并针对这些原因提出改进措施。
Under the background of pushing forward the prefabricated buildings in China,taking the project of Shanghai as an example,this paper contrasts the cost of prefabricated structure with cast-in-place structure,and analyzes the cause of the high cost of prefabricated components,finds out the main factors affecting the cost,finally puts forward improvement measures according to these causes.
作者
刘竞择
LIU Jingze(Capital Construction Department, Shanghai Jiao Tong University, Shanghai 200240, Chin)
出处
《工程经济》
2018年第5期9-11,共3页
ENGINEERING ECONOMY
关键词
建筑业
装配式结构
构件
成本控制
construction industry
prefabricated structure
component
cost control