摘要
袁店一井煤矿东风井井筒掘砌施工期间,采用混合悬吊的方式悬吊凿井设备,不仅节省了大量临时设备,还为井筒的顺利掘砌创造了良好条件,达到了安全、快速安全施工的目的。
During Yuandian Yijing coal mine Dongfeng shaft digging, the mixed suspension of sinking equipment,not only saves a large number of temporary equipment,but also created favorable conditions for the smooth shaft excavation,to achieve a safe,fast construction purpose.
作者
彭彭
冯旭东
周柳涛
Peng Peng;Feng Xudong;Zhou Liutao(NO.29 Construction Department of China Coal Mine Construction Group Corporation, Suzhou 234000, China;National Engineering Laboratory for Deep Shaft Construction Technology in Coal Mine, Huaibei 235000, China;China Coal Mine Construction Group Corportation Limited, Hefei 230022, China;China Coal No.71 Engineering Company Limited, Suzhou 234000, China)
出处
《煤矿机械》
北大核心
2018年第6期56-57,共2页
Coal Mine Machinery
关键词
立井施工
混合悬吊
井筒
钢丝绳
shaft construction
mixed suspension
shaft
steel wire rope