基于改进G1法—集对分析的水电EPC项目风险评价 被引量:1

Risk assessment of hydropower EPC project based on improved G1 method set and pair analysis
下载PDF
导出
摘要 为分析水电EPC项目风险状况,运用集对分析法对风险进行评价。从管理、政治、经济、技术、不可抗力五个方面建立评价指标体系,采用指数标度的改进G1法对指标进行赋权;构建五元联系数评价模型,计算集对势、分析态势等级,确定风险状况;以陕西省某水电站为例进行分析,结果表明综合风险等级为中等,且风险态势为同势61级,并制定相应控制措施,研究结果能为水电EPC项目风险管理提供决策支持。 In order to analyze the risk situation of hydropower EPC project,the set pair analysis method is applied to evaluate the risk. From the management,politics,economy,technology,force majeure,this five aspects of EPC hydropower project risk,establish the evaluation index system,the index weighting based on improved G1 index scale method; construction of five element connection number assessment model of project risk is conducted,calculate set pair potential,analyse trend level,determine the risk status; taking the EPC project of a hydropower station in Shanxi as an example,the results show that the risk level is moderate,and the risk level is the same level 61 levels,and the corresponding control measures are worked out. The research results can provide decision support for risk management of hydropower EPC project.
作者 马黎 李海佳 Ma Li;Li Haijia(College of Hydraulic & Environmental Engineering, Yichang 443002, China;Fifth Project of Gezhouba Dam Group Limited Company, Yichang 443002, China;China Railway Twenty-one Bureau International Engineering Limited Company, Beijing 100161, China)
出处 《山西建筑》 2018年第12期241-242,共2页 Shanxi Architecture
关键词 水电EPC项目 风险评价 改进G1法 集对分析 hydropower EPC project risk assessment improved G1 method set pair analysis
  • 相关文献

参考文献4

二级参考文献34

共引文献56

同被引文献5

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部