山岭隧道施工人员辐射剂量评估方法及应用 被引量:2

Evaluation Method for Radiation Dose of Workers during Mountain-crossing Tunnel Construction and Its Application
下载PDF
导出
摘要 为合理评估山岭隧道施工阶段的辐射对施工人员的影响,通过测试隧道内环境的γ辐射剂量率、空气氡浓度、粉尘质量浓度、围岩放射性核素比活度等环境参数,以工人年均个人剂量为主要评估指标,推荐了一套基于新奥法施工的山岭隧道施工阶段辐射对施工人员影响的评估方法。运用该方法对摩岗岭隧道不同施工工序下的各项辐射指标进行测试和评估,研究得出:摩岗岭隧道施工人员各工序年均个人剂量为0.203~1.13 m Sv,隧道内部辐射环境对施工人员的影响处于较低范围。该评估方法不仅考虑了隧道不同工序施工人员接受辐射时间、辐射来源等问题,而且辐射指标的选取符合山岭隧道施工的实际情况,对隧道穿越辐射异常区的施工安全和辐射防治具有指导作用。 In order to evaluate the radiation and its impacts on workers during mountain-crossing tunnel construction,a suit of evaluation methods applicable to the tunnel construction with New Austrian Tunneling Method( NATM) is recommended. The average individual radiation dose of tunnel workers per year is chosen as evaluating indicator,and the environmental factors including air radon concentration,environmental gamma radiation dose rate,dust concentration and radionuclides specific activity are tested. The above-mentioned assessment method is applied to the radiation environment of Mogangling Tunnel under different working processes. The assessment results show that the average individual radiation dose of workers in Mogangling Tunnel construction per year ranges from 0. 203 to 1. 13 m Sv;therefore,the impact of radiation environment on workers is relatively low. The assessment method in this study considers different irradiation time of tunnel workers in different processes as well as multifarious radiation sources,and the selection of radiation indicators meets the actual situation at the same time. The study results can provide guidance for construction safety and radiation control in tunnel construction at abnormal radiation area.
作者 徐华 唐垠斐 张鹏 李王斌 陈紫云 XU Hua;TANG Yinfei;ZHANG Peng;LI Wangbin;CHEN Ziyun(School of Civil Engineering, Southwest Jiaotong University, Chengdu 610031, Sichuan, China;Ganzi City Traffic Construction Investment Co. , Ltd. , Kangding 626000, Sichuan, China;Sichuan Communication Surveying & Design Institute, Chengdu 610017, Sichuan, China)
出处 《隧道建设(中英文)》 北大核心 2018年第5期776-781,共6页 Tunnel Construction
基金 交通运输部西部交通建设科技项目(2015318J29040) 甘孜州交通建设科技项目(MML2016001)
关键词 山岭隧道 施工环境 评价方法 辐射影响 mountain-crossing tunnel construction environment evaluation method radiation impact
  • 相关文献

参考文献8

二级参考文献30

  • 1王其亮.测量环境γ辐射剂量率扣除宇宙辐射响应的方法及误差的探讨[J].中华放射医学与防护杂志,1994,14(4):278-282. 被引量:3
  • 2王其亮,崔圣裕,樊小敏,钟志,邢亚军,王建超,胡爱英,周勇.航空机组人员的职业照射及危险估计[J].中国辐射卫生,1995,4(1):9-11. 被引量:3
  • 3王广才,侯胜利,刘成龙,王辉,王玉宝,颜新荣,王晓卫.某区放射性环境地质评价研究[J].工程地质学报,2006,14(1):96-100. 被引量:7
  • 4成都地质学院三系.放射性勘探方法[M].北京:原子能出版社,1978.90-91.
  • 5贾文懿.利用天然放射性找地下水[M].北京:原子能出版社,1986..
  • 6[2]L·米勒.岩石力学[M].北京:煤炭工业出版社,1981.
  • 7万骏,张锦由.核辐射测量学基础[J].华东地质学院,2000.
  • 8王其亮.中国天然辐射外照射水平及其在测量中应注意的一些问题[J].全国天然辐射照射与控制讨论会,2000,11.
  • 9谢宇平.第四纪地质学及地貌学[D].北京:地质出版社,2000.
  • 10高柏,周仲魁.放射性污染与防治.东华理工学院环境工程教研室,2005.

共引文献90

同被引文献22

引证文献2

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部