AP1000核电CR10模块整体吊装吊点布置与分析 被引量:1

Layout and analysis of integral hoisting points of CR10 module of AP1000 nuclear power station
下载PDF
导出
摘要 AP1000核电站CR10模块是大型桁架式钢结构,外形尺寸大、结构复杂,采用起重机整体吊装过程中易发生变形。针对以上难点,制定了吊装方案,运用有限元分析法对CR10模块吊点布置进行了对比计算,通过分析不同吊点布置对CR10模块应力和位移的影响,最终得到CR10模块整体吊装的最优吊点。 The CR10 module of AP1000 nuclear power station is of a large truss steel construction with large size and complex structure,which is easy to deform during the integral hoisting process by crane. In view of the above-mentioned difficulties,the hoisting scheme is set up,and the finite element analysis method is used to compare the hoisting point layout of the CR10 module. By analyzing the stress and displacement of the CR10 module at different hoisting points,the optimal lifting point of CR10 module is finally obtained.
作者 李豪 白朝阳 李超 钱红飚 孙绍琳 孟和苏乐德 Li Hao;Bai Zhaoyang;Li Chao;Qian Hongbiao;Sun Shaolin;Men Hesulede(Dalian Yiliya Construction Machinery Co. , Ltd. , Dalian 116025, Liaoning)
出处 《工程建设》 2018年第6期63-66,共4页 Engineering Construction
关键词 CR10模块 整体吊装 吊点布置 有限元分析 变形 CR10 module integral hoisting and installation layout of hoisting points finite element analysis deformation
  • 相关文献

参考文献1

二级参考文献2

共引文献3

同被引文献5

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部