关于大型纯凝式机组供热后的问题分析及改造 被引量:1

Problem Analysis and Reconstruction After the Heating of Large-Scale Pure Condensing Unit
下载PDF
导出
摘要 某发电厂的纯凝式机组从2017年7月开始向周边企业供热,期间产生了负荷波动下供热压力不稳定、供热蒸汽温度变化大、供热节流损失、安全阀频繁动作,以及减温减压阀门阀芯脱落等现象。在利用机组调停检修期间,通过供热系统的技术改造,增加了一路供热汽源,并加装了供热系统小旁路阀,解决了这些问题。 The pure condensing unit of a power plant began heating the surrounding enterprises since July2017,but some problems occurred,e.g.the heat supply pressure is unstable under load fluctuation,the heating steam temperature changes greatly,the heating and throttling have loss,the relief valve frequently movs,and the core of the temperature/pressure-releasing valve falls off.During the period of the unit′s adjustment and maintenance,through the technical transformation of the heating system,another heating source is supplied,and the small bypass valve of the heating system is added to solve these problems.
作者 沈霄华 秦涛 廖红涛 SHEN Xiaohua;QIN Tao;LIAO Hongtao(Changxing Power Plant, Huaneng International Electric Power Co. , Ltd. , Changxing 313100, China)
出处 《电力与能源》 2018年第3期440-442,共3页 Power & Energy
关键词 纯凝式机组 供热 负荷波动 pure condensing unit heating load fluctuation
  • 相关文献

参考文献2

二级参考文献3

共引文献6

同被引文献2

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部