基于ISM与AHP的斜拉桥主梁施工阶段风险分析 被引量:8

Risk Analysis on the Girder of Cable-Stayed Bridges at the Construction Phase: A Study Based on ISM and AHP
下载PDF
导出
摘要 以喀腊塑克水库特大桥为背景,运用解释结构模型(ISM)对该特大桥主梁施工阶段风险因素进行分析,通过建立多层递阶结构模型,明确风险因素上下级之间的关系,找出施工阶段中存在的表层、中间层和深层风险;再运用层次分析法(AHP)对主要的风险因素进行定性与定量的综合分析,通过对风险因素的权重比较,找出主要的风险源。结果表明:主梁施工阶段出现的风险因素中,施工技术风险和人因风险是影响主梁施工安全的主要风险,控制和监督主梁施工阶段的风险可以从这两点入手。合理、可靠的结论为该工程以及类似工程施工过程中的风险分析提供参考,以降低施工阶段风险发生概率。 Based on the background information of Kalasuke bridge, this paper analyzes the risk factors of the main girder of the bridge at the construction stage by using the interpretation structure model (ISM). Through establishing a multi-layer hierarchical structure model, the relationship between the upper and lower levels of risk factors is clarified, and the superficial, middle and deep risks emerging during the construction stage are identified. Then, we use analytic hierarchy process (AHP) to qualitatively and quantitatively analyze the main risk factors. By comparing the weights of these risk factors, we identify the primary risk sources. The results show that the construction technology risks and human factor risks are the primary risks affecting the construction safety of the main girder at the construction stage. The control on corresponding risks can start from these two points. The results of this study can provide references for the risk analysis during the construction process of Kalasuke bridge as well as other similar projects. As a result, the probability of risk occurrence can be reduced at the construction stage.
作者 杨珍珍 樊燕燕 YANG Zhen-zhen;FAN Yan-yan(School of Civil Engineering,Lanzhou Jiaotong University,Lanzhou 730070,Chin)
出处 《工程管理学报》 2018年第3期124-128,共5页 Journal of Engineering Management
基金 长江学者和创新团队发展计划(IRT15R29)
关键词 桥梁工程 ISM AHP 施工阶段 风险因素 bridge engineering ISM AHP construction stage risk factors
  • 相关文献

参考文献9

二级参考文献71

共引文献174

同被引文献54

引证文献8

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部