摘要 以某超五星国际酒店式公寓楼为工程实例,论述了板式预应力转换施工方法、层模架支撑体系、超高层大体积混凝土输送、布料方法、施工技术措施及资源配备,解决了混凝土浇筑量大、危险系数高、场地条件有限、施工复杂的问题,保证了转换层结构安全、高效施工及其以上结构受力和整体建筑性能与质量。 Taking the apartment building of some super-five-star International hotel as the example,the paper indicates the construction methods for the plate prestress transition,support system of layer modulus,transportation of super-high-rise large concrete,method for material laying,construction technical measures,so as to solve the problems in large grouting volume of concrete grouting,high danger coefficient,limited site conditions,and complicated construction,and ensure the safety of the transitional layer,effective construction and the performance and quality of the structural stress and whole buildings.
作者 陈新焱 Chen Xinyan(Shanxi Construction Investment Group Co.,Ltd,Taiyuan 030002,Chin)
出处 《山西建筑》 2018年第18期82-84,共3页 Shanxi Architecture
关键词 板式预应力 结构转换层 模架支撑 大体积混凝土 plate prestress structural transitional layer modulus support large concrete
  • 相关文献

参考文献1

二级参考文献2

  • 1GB50010-2002.混凝土结构设计规范[S].[S].,..
  • 2JGJ3-2002.高层建筑混凝土结构技术规程[S].[S].,..

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部