针对黑龙江省三莫公路亚雪路段改扩建工程施工期间由于碎石运输通道因特殊地理原因无法正常运达施工现场的问题,通过将价值工程评价与移动破碎施工工艺方案相结合的方法,对方案进行功能评价、成本评价及价值评价系数的计算,综合的评价施工方案的价值目标,从而确定与实际工程情况相适应的移动破碎方案,实现在确保工程材料顺利供应的同时使得改扩建道路沿途景观环境得到改善,在减少施工成本的同时因地制宜地利用现有施工条件确保整体施工的顺利进行。
The paper is based on San Mo in Heilongjiang province highway road reconstruction project in the snow. Because of the gravel transport channel due to special geographical reason not normal to arrive at the scene of the construction problems. By the value engineering evaluation combined with mobile crushing construction technology scheme. To function evaluation,cost evaluation scheme and the calculation of the coefficient of value evaluation,comprehensive evaluation of the construction scheme of value goal. To identify with the actual engineering situation of mobile crushing,and to ensure smooth supply of engineering materials at the same time make the road landscape environment along the reconstruction and improve. When reduce the construction cost,and construction of the existing conditions,according to local conditions to ensure that the overall construction smoothly.
作者
解世林
徐文远
肖阳
Xie Shilin;Xu Wenyuan;Xiao Yang(College of Civil Engineering,Northeast Forestry University,Harbin 150040,China;Southwest Branch of China ConstructionEighth Engineering Bureau,Chengdu 661141,China;Heilongjiang Provincial Highway Construction Bureau,Harbii 150036,China)
出处
《山西建筑》
2018年第18期114-117,共4页
Shanxi Architecture
基金
黑龙江省交通运输厅重点科技项目(2016HLJ020)
关键词
移动破碎
价值工程
施工方案
mobile crushing
value engineering
construction plan